Bunker Renovation Update

The bunker renovation project begins! Unfortunately, the untimely rains have made the work challenging. This weekend, we continued our efforts and we've accomplished a lot. The greenside bunkers on #10, #11, #12 and #14, #15 and #16 are ready for drainage, and sand can now be installed. We are anticipating our first delivery of sand on the property shortly, so we hope to have the remaining green side bunkers on the back side done to the point where new drainage can be installed. Here are a few pictures of the project.


Right hand bunker on 14 ready for tile and sand
Temporary trench dug to divert water away from bunker
Old drain trenches cleaned out ready for new drainage

#12 bunker ready for drainage

10 right side bunker old drain tile removed